Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 272: 2009-003-00 EXP YN - 6 MONTH STAFF & SUBS
Project Number:
Title:
Upper Columbia Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 20.00%
Methow 40.00%
Wenatchee 40.00%
Contract Number:
56662 REL 272
Contract Title:
2009-003-00 EXP YN - 6 MONTH STAFF & SUBS
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Issued
Contract Description:
This contract will supplement Contract 56662 REL 265 from December 1, 2022 to May 31, 2023 to cover YN Fisheries UCHRP staff costs, project overhead costs, and on-call service subcontract costs that were not fully funded in REL 265 due to an FY22 budget shortfall.  When REL 265 was completed in May 2022 a budget shortfall for the UCHRP in Fiscal Year 2022 required that many estimated project overhead costs and on-call service subcontracts ranging for a 12 month performance period be significantly reduced.  At that time, it was identified that a supplemental contract scheduled for a 6 month period in Fiscal Year 2023 could be used to ensure the reduced overhead items and on-call service subcontracts would become fully funded for the remainder of the REL 265 performance period.  This contract represents the 6 month supplemental budget to REL 265 which allows these on-going project expenses to be budgeted in FY23 instead of FY22.  Because this contract represents supplemental FY23 funding to the existing REL 265 contract, all BPA funded property inventory for the UCHRP is already reported under the REL 265 contract and an additinal property inventory will no be reported under this contract.

Please refer to the REL 265 contract description for more details about the purpose, need, and scope for this contract in supporting the Yakama Nation Upper Columbia Habitat Restoration Project through May 31, 2023.
Account Type(s):
Expense
Contract Start Date:
12/01/2022
Contract End Date:
05/31/2023
Current Contract Value:
$725,896
Expenditures:
$580,717

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Jason Breidert Yakama Confederated Tribes Yes Technical Contact brej@yakamafish-nsn.gov (509) 860-5351
Chris Butler Yakama Confederated Tribes Yes Technical Contact butlerc@yakamafish-nsn.gov (509) 449-8215
Christopher Clemons Yakama Confederated Tribes Yes Technical Contact clec@yakamafish-nsn.gov (509) 881-5746
Joseph Connor Bonneville Power Administration Yes F&W Approver jwconnor@bpa.gov (503) 230-3172
Annet Dillman Yakama Confederated Tribes No Administrative Contact dila@yakamafish-nsn.gov (509) 865-2255
Madeleine Eckmann Yakama Confederated Tribes Yes Technical Contact eckm@yakamafish-nsn.gov (509) 449-2091
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Jarred Johnson Yakama Confederated Tribes Yes Technical Contact johj@yakamafish-nsn.gov (509) 881-1462
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Brandon Rogers Yakama Confederated Tribes Yes Supervisor rogb@yakamafish-nsn.gov (509) 949-4109
Hans Smith Yakama Confederated Tribes Yes Contract Manager h.smith@methownet.com (509) 449-2750
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Manage personnel, property and subcontracts for overall UCHRP 05/31/2023 05/31/2023
Produce Conceptual Designs C: 175. UC Site Evaluation and Conceptual Engineering Contract - 2010-58 05/31/2023 05/31/2023
Rare Plant Surveys and Report D: 165. UC Rare Plant Surveys 2010-44 05/31/2023 05/31/2023
Chelan NRD Support/Outreach for Wenatchee Habitat Projects E: 191. Outreach Supporting Habitat Restoration Activities (Wenatchee) CCNRD 2012-98 05/31/2023 05/31/2023
Conduct Appraisals F: 172. UC Appraisals 2018-197 05/31/2023 05/31/2023
Produce Survey G: 172. UC Professional Land Survey Contract 2015-128 05/31/2023 05/31/2023
Provide Scientific Support for YN UCHRP Projects H: 122. UC On-Call Scientific Support (Review and Recommendation) 2016-159 05/31/2023 05/31/2023
Provide HAZ MAT Inspection I: 165. UC On-Call Haz Mat Review 2016-158 05/31/2023 05/31/2023
Provide Coordination on Restoration Work Proposed by the YN on WDFW Land J: 122. WDFW MOU Review 2016-157 05/31/2023 05/31/2023
Engineering Support Services K: 122. On-call Engineering Support Services 2009-17 05/31/2023 05/31/2023
Post Implementation Monitoring of Habitat Projects L: 115. UC Post Implementation Field Monitoring 2012-85 05/31/2023 05/31/2023
Groundwater pump tests complete M: 208. Install Piezometer Wells and Conduct Groundwater Pump Tests 2010-37 05/31/2023 05/31/2023
LWD Procurement and Hauling N: 29. Large Wood Procurement - 2010-59 05/31/2023 05/31/2023
Large Wood Stockpile Locations Secured by Rental Agreements O: 92. UC Large Wood Storage 2015-131 05/31/2023 05/31/2023
Produce Native Plant Restoration and Soil Bio-Engineering Design, Materials, and Installation P: 47. UC Native Plant Restoration and Soil Bio-Engineering - 2010-62 05/31/2023 05/31/2023
Conduct Geo-Tech Services Q: 186. UC Sheet Pile Geo-Tech 2012-83 05/31/2023 05/31/2023
On-Call Construction Services R: 186. UC On-Call Construction Services 2012-82 05/31/2023 05/31/2023
Inspect and repair wells S: 208. UC On-Call Well Inspection and Repair 2016-156 05/31/2023 05/31/2023
Tree Tipping Consuting and Implementation T: 29. UC Strategic Tree Recruitment Services 2022-216 05/31/2023 05/31/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 92 Lease Land
  • 2 instances of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 92 Lease Land
  • 2 instances of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Manage personnel, property and subcontracts for overall UCHRP
C 175 UC Site Evaluation and Conceptual Engineering Contract - 2010-58
D 165 UC Rare Plant Surveys 2010-44
E 191 Outreach Supporting Habitat Restoration Activities (Wenatchee) CCNRD 2012-98
F 172 UC Appraisals 2018-197
G 172 UC Professional Land Survey Contract 2015-128
H 122 UC On-Call Scientific Support (Review and Recommendation) 2016-159
I 165 UC On-Call Haz Mat Review 2016-158
J 122 WDFW MOU Review 2016-157
K 122 On-call Engineering Support Services 2009-17
L 115 UC Post Implementation Field Monitoring 2012-85 12/01/2022
M 208 Install Piezometer Wells and Conduct Groundwater Pump Tests 2010-37 12/01/2022
N 29 Large Wood Procurement - 2010-59 12/01/2022
O 92 UC Large Wood Storage 2015-131 12/01/2022
P 47 UC Native Plant Restoration and Soil Bio-Engineering - 2010-62 12/01/2022
Q 186 UC Sheet Pile Geo-Tech 2012-83 12/01/2022
R 186 UC On-Call Construction Services 2012-82 12/01/2022
S 208 UC On-Call Well Inspection and Repair 2016-156 12/01/2022
T 29 UC Strategic Tree Recruitment Services 2022-216 12/01/2022